Hi Carrie,
We are in 14.10 .We have set NoDot0Backdown = False in the control file.
Currently I created few Analyze jobs in stats manager for databases I enabled use count logging. The analyze job is running for a long time(almost 72 hours) and giving recommendations only for misssing and deactivate but not giving recommendations for stale stats
I have created analyze job based on PDCRDATA database with limit queries to 1 week
Why analyze jobs taking longtime ? do we need to enable any logging other than statsusage and usecount?
is this due to stats version 5 we are currently using?
Thanks
Chandrasekhar
managed services
Hi Carrie,
We are in 14.10 .We have set NoDot0Backdown = False in the control file.
Currently I created few Analyze jobs in stats manager for databases I enabled use count logging. The analyze job is running for a long time(almost 72 hours) and giving recommendations only for misssing and deactivate but not giving recommendations for stale stats
I have created analyze job based on PDCRDATA database with limit queries to 1 week
Why analyze jobs taking longtime ? do we need to enable any logging other than statsusage and usecount?
is this due to stats version 5 we are currently using?
Thanks
Chandrasekhar
managed services